M70i/M80i Hygienic Ball Valve Installation and Maintenance Guide | Spirax Sarco

Guidance for hygienic system personnel on the safe installation, commissioning, operation, and maintenance of M70i/M80i stainless steel ball valves.

Select model

Installation and Maintenance Instructions

  1. Safety Information
  2. General Product Information
  3. Installation
  4. Commissioning
  5. Operation
  6. Maintenance and Spare Parts

1. Safety Information

Safe operation of this product can only be guaranteed if it is properly installed, commissioned, and maintained by qualified personnel (see Section 1.11) in accordance with the operating instructions. General installation and safety instructions for pipeline and plant construction must also be followed, and tools and safety equipment must be used correctly.

1.1 Intended Use

Refer to the Installation and Maintenance Instructions, nameplate, and technical literature to verify that the product is suitable for its intended application. This product complies with the requirements of the European Pressure Equipment Directive (PED) and can bear the CE marking where required.

The product complies with the following Pressure Equipment Directive classifications:

ProductGroup 1 gasesGroup 2 gasesGroup 1 liquidsGroup 2 liquids
M70i ISO and M80i ISO1/2"SEPSEPSEPSEP
3/4"SEPSEPSEPSEP
1"SEPSEPSEPSEP
11/2"212SEP
2"212SEP
21/2"212SEP
3"212SEP
4"212SEP

i) This product is specifically designed for clean/pure steam and other high-purity systems classified as Group 2 under the Pressure Equipment Directive. It is also suitable for liquid systems classified as Group 1 under the Pressure Equipment Directive. The product may also be used with other fluids. Contact Spirax Sarco to confirm its suitability for the intended application.
ii) Check material suitability and the pressure and temperature limits. If the upper operating limit of the product is lower than the requirements of the system in which it is installed, or if product failure could result in hazardous overpressure or overtemperature, ensure that the system is fitted with suitable safety devices to prevent these limits from being exceeded.
iii) Ensure correct installation and fluid flow direction.
iv) Spirax Sarco products are not designed to withstand external stresses imposed by the system. The installer is responsible for considering potential stresses and taking adequate precautions to minimize them.
v) Before installation in steam or other high-temperature applications, remove all protective covers from the connections and the protective film from the nameplate.

1.2 Access

Before working on the equipment, ensure safe access and, if necessary, provide suitable lifting equipment.

1.3 Lighting

Ensure adequate lighting, particularly where detailed or complex work is required.

1.4 Hazardous Liquids or Gases in the Pipeline

Consider the medium in the pipeline and its condition. Take account of flammable substances, substances hazardous to health, and substances at extreme temperatures.

1.5 Hazardous Environment Around the Product

Consider explosion hazards, lack of oxygen (for example, in tanks or pits), extreme temperatures, hot surfaces, fire hazards (for example, during welding), excessive noise, and moving machinery.

1.6 The System

Consider the effect of the intended work on the complete system. Determine whether any action, such as closing an isolation valve or performing electrical isolation, could place other parts of the system or personnel at risk.

Hazards may include isolation of vents or protective devices and failure of controls or alarms. Ensure that valves are opened and closed gradually to avoid system vibration.

1.7 Pressure Systems

Ensure that system pressure is isolated and safely vented. Consider double isolation (double block and bleed) and the locking or labeling of closed valves. Do not assume that the system is depressurized merely because the pressure gauge indicates zero.

1.8 Temperature

After isolating the valve, allow sufficient time for it to cool to ambient temperature to prevent burns.

When operated above 260 °C (500 °F), PTFE components release toxic fumes that can cause discomfort if inhaled. Smoking is prohibited in areas where PTFE is stored, handled, or processed. If tobacco contaminated with PTFE particles is smoked, inhalation of the fumes can cause a condition known as polymer fume fever.

1.9 Tools and Spare Parts

Before starting work, ensure that suitable tools and consumables are available. Use only genuine Spirax Sarco spare parts.

1.10 Protective Clothing

Consider whether operators or nearby personnel require protective clothing to guard against hazards such as chemicals, high or low temperatures, radiation, noise, falling objects, and injury to the eyes or face.

1.11 Permit to Work

All work must be carried out or supervised by qualified personnel.

Installation and operating personnel must be trained in the correct use of the product in accordance with its Installation and Maintenance Instructions.

A formal permit-to-work system must be followed. Where no such system exists, the person responsible should understand the work to be performed and determine where a person with specific responsibility for safety is required.

Post warning notices where necessary.

1.12 Handling

Manual handling of large and/or heavy products may present a risk of injury. Lifting, pushing, pulling, striking, or supporting a load using the body can cause injury, particularly to the back. It is recommended that the risks be assessed with consideration given to the task, personnel, load, and working environment, and that appropriate handling methods be used.

1.13 Residual Heat

During normal operation, the external surface of this product may become very hot. When operated at the maximum allowable conditions, the product surface temperature may reach 200 °C (392 °F).

These products are not self-draining. Exercise caution when dismantling or removing the product from the pipeline (refer to the “Maintenance Instructions”).

1.14 Freezing

Products that are not self-draining must be protected against freezing when used in applications where the ambient temperature may fall below the freezing point.

1.15 Disposal

Unless otherwise specified in the Installation and Maintenance Instructions, this product is recyclable, except for PTFE, and presents no ecological hazard provided it is disposed of correctly.

PTFE:

  • Dispose of PTFE only by an approved method. Do not incinerate it.
    Store PTFE in a separate container, do not mix it with other waste, and deliver it to an approved waste disposal facility.

1.16 Returning Products

Customers and distributors returning products to Spirax Sarco must comply with UK and EC health, safety, and environmental regulations. Where contamination by hazardous residues or mechanical damage may present a health, safety, or environmental hazard, information must be provided regarding the hazards and the precautions to be taken. This information must include safety data for any substances identified as hazardous to health or safety.

2. General Product Information

2.1 Introduction

M70i and M80i 316L ISO and ASME BPE valves are intended for liquid, gas, and process-support applications, including clean steam.* These valves must be used as isolation valves, not as control valves.

ISO mounting

The integral ISO mounting allows the valve to be automated without dismantling the valve body, thereby maintaining sealing integrity. Fitting a Spirax Sarco BVA300 series pneumatic actuator enables straightforward conversion from manual to automatic operation. Contact Spirax Sarco for further information.

Standards:

The product fully complies with the European Pressure Equipment Directive (PED). The CE marking is available where required.

Certification:

The following certificates are available:

  • EN 10204 3.1 material certificate
  • FDA/USP elastomer compliance certificate
  • Surface finish certificate

Note:

All certification and inspection requirements must be specified when placing the order.

Available Models

M70iV CF ISOVirgin PTFE TFM 1600 with cavity fillers
M70iVEP CF ISOVirgin PTFE TFM 1600, electropolished to 0.375 micrometers Ra, with cavity fillers
M70iG CF ISOMineral-filled PTFE with cavity fillers
M70iGEP CF ISOMineral-filled PTFE, electropolished to 0.375 micrometers Ra, with cavity fillers
M70iV ISOVirgin PTFE TFM 1600
M70iVEP ISOVirgin PTFE TFM 1600, electropolished to 0.375 micrometers Ra
M70iG ISOMineral-filled PTFE
M70iGEP ISOMineral-filled PTFE, electropolished to 0.375 micrometers Ra
M80iVEP ISOVirgin PTFE TFM 1600, electropolished to 0.375 micrometers Ra
M80iVEP CF ISOVirgin PTFE TFM 1600, electropolished to 0.375 micrometers Ra, with cavity fillers

2.2 Sizes and Pipeline Connections

M70i 1/2", 3/4", 1", 11/2" and 2"Sanitary clamp connections (ASME BPE)
Extended O/D butt-weld tube ends (ETO) (ASME BPE).
M80i 21/2", 3" and 4"Sanitary clamp connections (ASME BPE)
Extended O/D butt-weld tube ends (ETO) (ASME BPE).

*Note: Steam service: Cavity fillers are not recommended for steam system applications.

M70i ISO 1/2" to 2" ball valve outline drawing

Figure 1 M70i ISO - 1/2”, 3/4”, 1”, 1 1/2”, and 2”

Note: The 3” and 4” end connections have a different design and are fitted with six bolts.

Figure 2 M80i ISO - 2 1/2”, 3”, and 4”

2.3 Limiting Conditions

M70i/M80i ISO pressure and temperature limiting conditions diagram

The product must not be used in this region.

A - B Virgin PTFE TFM 1600

A - C PTFE

*Note: Steam service: Cavity fillers are not recommended for steam system applications.

Body design conditionsM70iPN63
M80i720 psi g
PMAMaximum allowable pressureM70i62 bar g @ 20 °C(899 psi g @ 68 °F)
M80i50 bar g @ 109 °C(720 psi g @ 228 °F)
TMAMaximum allowable temperatureM70i200 °C @ 0 bar g(392 °F @ 0 psi g)
M80i180 °C @ 0 bar g(356 °F @ 0 psi g)
Minimum allowable temperatureM70i-29 °C(-20 °F)
M80i-20 °C(-4 °F)
PMOMaximum operating pressure for saturated steam service *M70i ISOVirgin PTFE TFM 16007.0 bar g
Mineral-filled PTFE8.5 bar g
M80i ISOVirgin PTFE TFM 16007.0 bar g
TMOMaximum operating temperatureM70i200 °C @ 0 bar g(392 °F @ 0 psi g)
M80i180 °C @ 0 bar g(356 °F @ 0 psi g)
Minimum operating temperatureM70i-29 °C(-20 °F)
M80i-20 °C(-4 °F)

Note: Consult Spirax Sarco for operation at lower temperatures.
DPMX, the maximum differential pressure, is limited by PMO.

3. Installation

Note: Before installation, carefully read the “Safety Information” in Section 1.

Although the valve has a robust design, tensile stress caused by pipe misalignment or incorrect pipe length will adversely affect the valve and must be avoided. Take particular care to ensure that the pipework is correctly aligned and that the pipe and valve are on the same axis.

The valve is intended for on/off applications and is manually operated.

Allow sufficient clearance around the installed valve for operation and maintenance.

Before installing the valve, verify that its size, pressure rating, material, connection type, and other specifications are suitable for the application.

Before installation, remove any contaminants that may have accumulated in the ball valve during storage. Maintain cleanliness throughout installation, as contaminants may damage the valve seats and operating mechanism.

To reduce valve seat wear caused by abrasive particles, install a strainer upstream of the ball valve.

When installing the valve, ensure that the handle is in a suitable position. The ideal position is with the handle vertical. For gas service, the ball valve may be installed in any orientation (see Figure 4).

For steam service:

(Ball valves fitted with cavity fillers are not recommended for steam systems.)

  1. Install a drain point upstream of the ball valve.
  2. Open the ball valve slowly to avoid water hammer.

For liquid systems, the valve must not be installed upside down (Figure 3).

Incorrect installation orientation for liquid systems

Figure 3 Incorrect installation for liquid systems

The valve must be fully closed before installation in the pipeline.

Open the ball valve slowly to avoid system shock.

Correct installation orientation for gas systems

Figure 4 Correct installation for gas systems

4. Commissioning

After installation or maintenance, ensure that the system is fully operational. Test all alarm and protective devices.

5. Operation

The ball valve is manually operated using the handle. During operation, take particular care to move the handle in the correct direction.

The valve is intended for on/off service and may be placed in either the fully open or fully closed position.

6. Maintenance and Spare Parts

Note: Before carrying out any maintenance work, read the “Safety Information” in Section 1.

6.1 Introduction

As with all mechanical equipment, regular maintenance is the most effective way to ensure continuous and efficient operation.

Inspect all valves regularly, particularly those that are used infrequently.

6.2 Routine Maintenance

The complete valve does not need to be removed from the pipeline for maintenance. Remove the two upper bolts and nuts (see item 1 in the parts table) and loosen the two lower bolts. Remove the complete body assembly and install the new parts. See Sections 6.3 and 6.4 for M70i ISO and M80i ISO spare parts and maintenance instructions.

6.3 M70i ISO Spare Parts and Maintenance Instructions

6.3.1 Available Spare Parts

Parts shown with solid lines are available as spares. Parts shown with dashed lines are not available as spares.

M70i ISOSeat and stem seal kit5, 6, 16, 18
M70i CF ISOSeat and stem seal kit with cavity fillers5, 6, 15, 16, 18

Ordering Spare Parts

Order spare parts using the description given above, and specify the ball valve model and size.

Example: 1 - ½” M70i CF ISO forged stainless steel ball valve, virgin PTFE TFM 1600, seat and stem seal kit with cavity fillers

M70i ISO spare parts exploded view

Figure 5 M70i ISO spare parts exploded view

6.3.2 Replacing the Seats and Body Gaskets (and Cavity Fillers, If Fitted)

  • Remove the valve body as described in Section 6.2.
  • Remove the valve body, seats (5), and body gaskets (16).
  • Install the new seats (5) and body gaskets (16), pressing them into the valve body recesses.

6.3.3 Replacing the Stem Seals

  • Remove the valve body as described in Section 6.2.
  • Ensure that the valve is in the closed position.
  • Remove the stem nut (10).
  • Remove the handle (12) and locking washer (9).
  • Remove the gland nut (8).
  • Remove the Belleville washer (17) and washer (7).
  • Remove the seats (5), body gaskets (16), and cavity fillers (15), if fitted.
  • Push the ball to either side and remove it (3).
  • Push the stem (4) down through the valve body cavity (1) and remove it.
  • Replace the stem seals (6 and 18).

M70i ISO exploded view of components with cavity fillers

Figure 6 M70i ISO with cavity fillers

6.3.4 Reassembly

Reassemble by following the instructions above in reverse order. Ensure that the bolts and nuts (14) are tightened to the recommended torque specified in Table 1.

Retighten the body bolts after 24 hours of operation.

6.4 M80i ISO Spare Parts and Maintenance Instructions

6.4.1 Available Spare Parts

Parts shown with solid lines are available as spares. Parts shown with dashed lines are not available as spares.

M80i ISOSeats, stem seals, stem O-ring, body seal kit, seal compression ring, and thrust washer5, 6, 11, 16, 18, 19
M80i CF ISOIntegral seats and cavity fillers, stem seals, stem O-ring, body seal kit, seal compression ring, and thrust washer5a, 6, 11, 16, 18, 19

Ordering Spare Parts

Order spare parts using the description given above, and specify the ball valve model and size.

Example: 1 - 4” M80iV ISO cast stainless steel ball valve, integral seats and cavity fillers, stem seals, stem O-ring, body seal kit, seal compression ring, and thrust washer

Figure 7 M80i ISO spare parts exploded view

M80i ISO 2 1/2" ball valve spare parts exploded view

6.4.2 Replacing the Seats and Body Gaskets

  • Remove the valve body as described in Section 6.2.
  • Remove the valve body, seats (5), and body gaskets (16).
  • Install the new seats (5) and body gaskets (16), pressing them into the valve body recesses.

6.4.3 Replacing the Stem Assembly

  • Remove the valve body as described in Section 6.2.

  • Ensure that the valve is in the closed position.

  • Remove the stem nut (10).

  • Remove the handle (12) and locking washer (9).

  • Remove the gland nut (8).

  • Remove the Belleville washer (17) and washer (7).

  • Remove the seats (5/5a) and body gaskets (16).

  • Push the ball to either side and remove it (3).

  • Push the stem (4) down through the valve body cavity (1) and remove it.

  • Replace the stem seals (6), stem O-ring (11), seal compression ring (18), and thrust washer (19).

6.4.4 Reassembly

Reassemble by following the instructions above in reverse order. Ensure that the bolts and nuts (14) are tightened to the recommended torque specified in Table 1.

Retighten the body bolts after 24 hours of operation.

Figure 8
M80i ISO stem assembly exploded view

FAQ

How should M70i and M80i hygienic ball valves be selected by pipe size and connection type?

The M70i is available in 1/2, 3/4, 1, 1-1/2, and 2 inch sizes, while the M80i is available in 2-1/2, 3, and 4 inch sizes. Both are available with ASME BPE-compliant hygienic clamp connections and extended OD butt-weld tube ends (ETO). Selection should match the pipe size, connection type, operating pressure, and operating temperature. The model must not be selected solely by size.

How should the seat material and cavity filler be selected when the M70i/M80i is used with saturated steam?

For the M70i with virgin PTFE TFM 1600, the maximum saturated steam operating pressure is 7.0 bar g; with mineral-filled PTFE, it is 8.5 bar g. For the M80i with virgin PTFE TFM 1600, the maximum saturated steam operating pressure is 7.0 bar g, where bar g denotes gauge pressure. CF models with cavity fillers are not recommended for steam applications. These steam operating pressures differ from the maximum allowable body pressure, and the body pressure rating must not be used in place of the steam service limit.

What configuration differences do V, G, EP, and CF indicate in M70i/M80i model designations?

V models use virgin PTFE TFM 1600, while G models use mineral-filled PTFE. EP models have an electropolished surface with a surface roughness of Ra 0.375 micrometers. CF models include cavity fillers. Available M70i models include V and G versions with EP and CF combinations. The listed M80i models are M80iVEP ISO and M80iVEP CF ISO. Sealing material, surface finish, and cavity filler requirements should be checked separately during selection.

Can the M70i/M80i be used for flow control or converted from manual to pneumatic operation?

The M70i/M80i is intended for isolation and on/off service and must be operated either fully open or fully closed. It must not be used as a flow control valve. Its integral ISO mounting arrangement allows an actuator to be installed without removing the valve body. A Spirax Sarco BVA300 Series pneumatic actuator can be fitted to convert the valve from manual operation to automated on/off operation. Adding an actuator does not change its intended use as an isolation valve.

What key precautions should be observed when installing and maintaining the M70i/M80i?

During installation, ensure that the piping and valve are coaxially aligned to prevent external loads caused by pipe misalignment or strain, and provide sufficient space for operation and maintenance. Remove debris before installation, and install a strainer upstream to reduce particle-induced seat wear. The valve must not be installed upside down in liquid systems. In steam systems, provide a drain point upstream and open the valve slowly to prevent water hammer. Before maintenance, isolate the valve from pressure, safely depressurize the system, and allow it to cool to ambient temperature. A zero pressure gauge reading alone must not be taken as confirmation that the system has been depressurized. For routine maintenance, the valve body assembly can be removed without removing the entire valve from the pipeline. After reassembly, retighten the body bolts after 24 hours of operation. Installation and maintenance must be performed or supervised by qualified personnel.

Documents

Recommended products

Our Contact Details

Click email or phone to copy. You can also scan WhatsApp / WeChat.

WhatsApp QR code WhatsApp
SteamVendor WeChat QR code WeChat